Our bricks, plaster and skirts have been completed. We are waiting for rendering and painting now.
The shower bases are also completed. Our cabinets are due for installation early next week and stair case the following week.
VV's Henley Homes Build
The Sahara Q1 - Belmont Fascade
Sunday, 6 January 2013
Wednesday, 14 November 2012
More progress on bricks
They have finished bricking the front fascade and all around on the first floor. SS told us that they will aim to finish the bricking this week and install the insulation next week followed by plastering.
We booked in for an private inspection early next week. Fingers crossed.
We booked in for an private inspection early next week. Fingers crossed.
Friday, 9 November 2012
Thursday, 8 November 2012
First floor bricking almost completed
They have almost completed the first floor bricking. Our SS advise that our bricking for the house should be completed by the end of next week followed by insulation.
Wednesday, 7 November 2012
Brick Stacker Doors and Fascade
Wednesday, 31 October 2012
Roof tiling almost complete
Sunday, 28 October 2012