Drove pass yesterday and more work has been done on the slabs. We are looking good for concrete pouring today.
Tuesday, 25 September 2012
Monday, 24 September 2012
Slab work Day 1
Finalling seeing some progress today. Looks like they did a lot of work in prepration for Wednesday's concrete pouring.
Wednesday, 19 September 2012
Sunday, 16 September 2012
Pipes Completed
Our pipes has just been completed as of 14th of September. However, our fence and permit is still not up yet.
We have also been told by our SS that the slabs will be poured on the 20th of September.
We have also been told by our SS that the slabs will be poured on the 20th of September.
Tuesday, 11 September 2012
Weekend Snaps
Visited Clyde North again on the weekend and took a few more photos. Please excuse my bad photography.
First day - Site Scrape
This is the first day Henley has been on site. They have just finished scraping the land for slab works on Friday. Surprisingly there are no signs up but we do have a portaloo. Yay! Definitely feeling the excitement now.
Thursday, 6 September 2012
On site scheduled
Henley has just informed us that we will be scheduled to have our slabs poured on the 14th.
We are super excited and should see them on site very shortly.
We are super excited and should see them on site very shortly.
Sunday, 2 September 2012