They have nearly finished tiling our roof. The tilers said they are about a day away from finishing.
Hopefully our bricks will be delivered tomorrow or next week.
Wednesday, 31 October 2012
Sunday, 28 October 2012
Thursday, 25 October 2012
Roof Tiles Delivered
Our roof tiles has been delivered. They have also finished installing the gutters on the ground and first floor.
Wednesday, 24 October 2012
Gutter Started
They have started to install our gutters. We have been told our tiles should be delivered shortly.
We also noticed a pipe sticking out of the WIR downstairs. It's in the way of the door. Any clue what it might be? It's on our drawings...
We also noticed a pipe sticking out of the WIR downstairs. It's in the way of the door. Any clue what it might be? It's on our drawings...